Coporal K.D. currently doesn't have toilet facility for his own home and shares his parent's toilet next door with another family nearby and walks few hundred yards to that toilet when needed. He can make his way around the house but cannot recognise objects or persons. Also he takes time to respond.
An initial estimate of some Rs. 200,000.00 was done by a local builder some 7 months ago at the request of a potential donor, which was never fulfilled. Ranaviru Fund identified Corporal K.D.'s requirement of a new wash room with a high priority. A new wash room of 7'x7'x8' was planned, designed and estimated to be completed within maximum of Rs. 150,000.00. Ranaviru Fund has provided the initial funds and the construction of the new wash room was started on the 06th of September.
Corporal K.D's wash room construction was completed as of 04 Nov 2009.
- A new building is required
|
Approximate sizes 7'x7'x8' |
Completed as of 04 Nov 2009 |
- A new cesspit is required
|
|
Completed as of 04 Nov 2009 |
- Pipe water to be provided
|
|
Completed as of 04 Nov 2009 |
- Commode & wash basin to be fitted
|
Provided by the Ranaviru Fund |
Completed as of 04 Nov 2009 |
- Fully tiled floor & walls
|
Provided by the Ranaviru Fund |
Completed as of 04 Nov 2009 |
|